New Service Connections

Please visit Development Information regarding general development information about the scope of your project.

If you are engineering a larger project and require specifications, see Construction Specifications.

The process for obtaining new water service generally follows these steps:

  1. Determine your project's water service and meter requirements.

  2. Complete and submit the Meter Installation Request Form with site and floor plans.

  3. Wait for Avion Water to review and approve your site plan. (please allow 5-7 business days)

  4. Obtain the approved site plan and Willing and Able to Serve Letter, if needed, for permitting.

  5. Pay applicable System Development Charges (SDCs) and estimated meter installation costs.

  6. Schedule and complete meter installation.

  7. Begin water service and assume responsibility for applicable monthly charges.

For more information regarding new service connections, visit New Water Service Process.